Which process can take place during a release review workshop?
Which process can take place during a release review workshop?
Managing a stage boundary can take place during a release review workshop as it involves reviewing the progress and planning for the next stage. This process looks both backwards to assess what has been achieved and forwards to plan future activities, making it integral to the release review. This allows the team to evaluate performance, quality, and benefits, and to ensure alignment with project goals moving forward.
The answer to the question "Which process can take place during a release review workshop?" in PRINCE2 Agile Foundation is B. Managing Product Delivery. During a release review workshop, the team can review the product or increment that has been produced and delivered so far and this process falls under the Managing Product Delivery process of PRINCE2 Agile. Chat GTP
The correct answer must be MB (Managing a stage boundary): Stage boundaries enables the team to look both forwards and backwards. Looking backwards, it helps the team understand: How did we do? How much was delivered? To what quality? What benefit was delivered? Did the process work well? Release reviews and retrospectives?
In 19.3.3 "Reporting of progress at the end of a sprint or a release is done via the sprint or release review and the optional product demo, which provides the opportunity to discuss planned features which were not delivered or those that were but were not originally planned for the release." so it seems that release review is held during Controlling a Stage, so maybe the correct answer is A.
C: Managing a stage boundary (ref 21.3)
Managing a stage boundary: Is it worth carrying out a formal workshop to review the management stage (perhaps as part of a release review) and then plan the next management stage