Which is a minimum requirement for applying the change theme?
Which is a minimum requirement for applying the change theme?
The minimum requirement for applying the change theme is to define the project's approach to baselining products. This involves specifying how product baselines are created, maintained, and controlled. Establishing a clear approach ensures that any changes to the project deliverables are managed systematically, thus maintaining the integrity and traceability of the project's scope.
I think not all Issues need to be registered in issue register. and some of them can be registered in the daily log
and option D says, only those issues, which raised to the issue register. so D is correct.
C is correct. D says to maintain the issue register, not to record every issue there. B is incorrect too, as the change authority does not have to be the PM
C is the correct answer. It cannot be D because only the formal issues are recorded in the issue register. The informal, are registered in the daily log.
C is correct, "Define how product baselines are created, maintained and controlled"
c looks correct
Issues do not need to be recorded in the issue register if they have been sufficiently covered in the issue report. The answer is C .
I think both are correct: C: The project (under the Change theme) should define how product baselines are created, maintained and controlled. D: Ensure that issues are captured, examined, managed and reviewed throughout the project
". To define the project's approach " is not correct i believe
C and D are correct according to the PRINCE2 manual, section 11.2: • define how product baselines are created, maintained and controlled • maintain some form of issue register to record identified issues and decisions relating to their analysis, management and review • ensure that project issues are captured, examined, managed and reviewed throughout the project lifecycle
D is the right answer. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes#theme-6 Minimum requirements You must define a risk management approach covering the risk management procedure to be used, and the roles and responsibilities for risk management. You must maintain some form of risk register to record and manage risks and must ensure that risks are identified, assessed, managed and reviewed throughout the project. You must use lessons to inform risk identification and management.
B seems to be correct. As stated in section 11.2: "define how product baselines are created, maintained and controlled"
But D is also correct as it says "maintain some form of issue register to record identified issues and decisions ..."