Question 36

The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.''

In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''.

Is this appropriate, and why?

    Correct Answer: A

    The risk response chosen is appropriate because delivering the 'e-learning course' incrementally as parts of the 'classroom-based training' gain accreditation will mitigate the impact of the threat. This approach ensures that work on the 'e-learning course' is not entirely dependent on the complete accreditation of the 'classroom-based course', which can effectively reduce the potential delay in delivering the 'accredited e-learning course' in time for the 'pilot courses'.

Discussion
suneeOption: C

C is correct. ref page number 132-10.4.3

anti8Option: C

Not B, C is correct

ManikRoyOption: C

As per 10.4.3 The plan step involves identifying and evaluating the appropriate risk response

RajPathakOption: C

I think it's C

Ciluba

Decide a risk response in 'Implementation' stage?

PieroBeOption: C

It is C, ref. 10.4.3. In the planning phase we are deciding the type of response for each identified (and assessed) risk.