Which is a true statement about PRINCE2 event-driven controls?
Which is a true statement about PRINCE2 event-driven controls?
Event-driven controls in PRINCE2 are used for decision making. These controls occur when a specific event happens, such as the end of a stage or the completion of a major project document. This allows the project board or project manager to make necessary decisions based on the event. Thus, the statement that event-driven controls are used for decision making is correct.
-Types of controls • Event-driven Takes place when a specific event occurs: - End of a stage - Completion of the Project Initiation Documentation (PID) • Time-driven Takes place at pre-defined periodic intervals: - Highlight Reports - Checkpoint Reports