Question 80

Who is responsible for the initial creation of the Configuration Item records?

    Correct Answer: A

    The Project Manager is responsible for the initial creation of the Configuration Item records. They are in charge of setting up and defining the project's configuration management strategy from the beginning, including the identification and creation of new configuration items. Project Support primarily provides administrative assistance and helps with storage and retrieval but does not typically create these records initially.

Discussion
PieroBeOption: D

ref table 16.3

ravi_awsOption: A

A Initial creation is done by the Project Manager Maintenance and updates are done by the Team Manager throughout the project Project Support provides administrative assistance by storing, filing, and retrieving Configuration Item Records as needed. They provide support to the Project Manager and Team Manager.