Question 38

When should PRINCE2 Agile be used?

    Correct Answer: A

    PRINCE2 Agile should be used when a team is created to deliver a specific product. This methodology combines PRINCE2's structured project management approach with the flexibility of agile practices, making it suitable for projects where requirements may evolve and there is a need for iterative progress. This is particularly effective for new projects requiring close collaboration and adaptability.

Discussion
DjtomipOption: A

why u guys dont give feedback to our commments!!??

darthhansieOption: A

Should be A PRINCE2 Agile is best suited for projects that require a flexible, iterative approach to delivery, where requirements may change frequently, and where there is a need for close collaboration between the project team and the customer or end-user. Therefore, PRINCE2 Agile is most appropriate when delivering new products, services, or systems that are complex, uncertain, or where there is a significant degree of innovation involved. It can also be used in situations where there is a need for ongoing maintenance or enhancement of an existing product or service, as long as there is a requirement for agility and flexibility in the delivery process.

Old_JediOption: A

The correct answer should be A

CFTOption: A

Why is this not A? Established teams are business as usual, which should not be governed by project management.