ABC Company's development team are using an agile delivery approach to produce the 'classroom-based training materials'. They have asked if their existing product owner can also act as team manager for their work package, although the team will continue to organize its own work within delegated limits of authority.
The project manager has agreed to this request.
Is this an appropriate action, and why?