Which 2 statements apply to either the Reporting arrangements or Problem handling and escalation sections?
Which 2 statements apply to either the Reporting arrangements or Problem handling and escalation sections?
Replace entry 8 with 'Checkpoint Report every Monday by 10.00 am' because Highlight Reports are intended for the Project Board. The PRINCE2 progress report from the Team Manager to the Project Manager is the Checkpoint Report, not the Highlight Report. Move entry 10 to Problem handling and escalation because that section describes how issues are handled. This ensures that any issues are categorized correctly and managed appropriately under the problem handling process.
A Correct:The PRINCE2 progress report from the Team Manager to the Project Manager is the Checkpoint Report and not the Highlight Report. B Incorrect:Reporting arrangements should contain details of the contents required, including products worked on. Correct:Anything to do with issues should come under the Problem handling and escalation section. Ref. A.26.2 D Incorrect:The recording of risks should be added to the Problem handling and escalation section, not the Reporting arrangements section. Ref. A.26.2. E Incorrect: Issues should be notified immediately. The impact analysis will take place afterwards.
the recording of risks is typically included in the Reporting arrangements section1. This is because it’s important for the Project Manager to be aware of any risks that have been identified during the course of work, and this information is usually included in regular reports. On the other hand, the Problem handling and escalation section is more about how issues will be escalated to the Project Manager1. This typically involves operational problems or issues that need immediate attention, rather than potential risks that might affect the project in the future.
Solution is A&C
the correct statements are: C. Move entry 10 to Problem handling and escalation because that section describes how issues are handled. D. Add ‘Any risks identified to be added to the Risk Register’ to Reporting arrangements.