PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 251


Which theme establishes the mechanisms to control against baselines by providing a forecast for the project’s objectives and continued viability?

Show Answer
Correct Answer: D

The purpose of the Progress theme is to establish mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives and the project’s continued viability, and control any unacceptable deviations. This theme is integral to ensuring the project remains on track and any necessary adjustments are made in a timely manner.

Discussion

5 comments
Sign in to comment
Risto83Option: D
Dec 26, 2022

The purpose of the progress theme is to establish mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives and the project’s continued viability, and control any unacceptable deviations.

Ro96Option: A
Dec 9, 2022

Should be A

Risto83Option: D
Dec 26, 2022

D 12.1 The progress theme

MyName_Option: D
Jul 2, 2023

The correct answer is Option D. Progress theme contents are pretty clearly articulated

bes_iOption: D
Jul 21, 2024

D is correct