The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.

Is this appropriate, and why?

Show Answer
Correct Answer: A

It is appropriate for the project manager to request an audit of the product because the project should verify that the recorded status reflects the actual status of the products. This ensures that there are no discrepancies between what is recorded and the actual state of the products, maintaining the integrity and accuracy of the configuration item records.

Discussion

5 comments
Sign in to comment
PieroBeOption: A
Jul 25, 2023

Ref 11.3.3

ManikRoyOption: A
Oct 2, 2023

11.3.3 It is good practice to periodically verify that the actual status of products reflects the authorized state of products as they are registered in the configuration item records, looking for any discrepancies. This is usually through reviews or audits, typically undertaken at the end of each stage and at the end of the project.

ravi_awsOption: A
Oct 9, 2023

In this case, it is appropriate for the project manager to request an audit of the product as well because the project manager should verify that the recorded status reflects the actual status of the products 1 . Therefore, the correct answer to the question is A: Yes, because the project should verify that the recorded status reflects the actual status of the products.

timedoutOption: A
Oct 15, 2021

B seems incorrect, can anyone confirm?

timedout
Nov 14, 2021

Aaah ok CI's are part of Change Control, so in the approach.