The contract with the external consultancy for the 'e-learning course' states that payments will be made to the supplier on completion of specified milestones as defined in the stage 3 plan. The project manager is concerned that there is insufficient detail in the team plan to enable the milestone payments to be aligned with the stage plan. As a result, the project manager has asked the team manager to include this information in the team plan and discuss the revised plan with the senior supplier before resubmitting it.
Is this a correct application of the team plan, and why?