Question 226

The contract with the external consultancy for the 'e-learning course' states that payments will be made to the supplier on completion of specified milestones as defined in the stage 3 plan. The project manager is concerned that there is insufficient detail in the team plan to enable the milestone payments to be aligned with the stage plan. As a result, the project manager has asked the team manager to include this information in the team plan and discuss the revised plan with the senior supplier before resubmitting it.

Is this a correct application of the team plan, and why?

    Correct Answer: A

    Yes, because the team plan should include the required contractual milestones. This ensures that the project manager can align payments and track progress effectively according to the contract. Including these milestones in the team plan helps in providing clear direction and avoids potential delays or disputes related to payment schedules.

Discussion
ravi_awsOption: A

Yes, because the team plan should include the required contractual milestones.