Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
The step in the issue and change control procedure that considers alternative options for responding to an issue being managed formally is 'Propose.' This step involves evaluating different courses of action after understanding the impact of the issue.
Answer is C: 11.4.3 Proposing corrective actions After a full understanding of the impact of the issue has been gained, the next step is to consider alternative options for responding to it and proposing a course of action to take.
Answer C