Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 148

Which is a factor when deciding the duration of a management stage?

    Correct Answer: B

    The level of risk in the project is a significant factor when deciding the duration of a management stage. High-risk projects typically benefit from shorter management stages to allow for more frequent assessments and reviews by the project board, ensuring that risks are monitored and managed effectively. This helps maintain control over the project's progress and makes it easier to mitigate potential issues.

Discussion
JasonbahrOption: B

B is correct. "The number of management stages within a project is clearly a balance between risk and cost as well as other factors. For example a high risk project would tend to have shorter management stages since the project board would want to review progress and the overall project status more often."

SGN63Option: B

B is correct

peppeOption: B

B is correct

Martin77Option: B

B is correct, according to the linked resource - " By observing which risks may occur in which of the management stages, decisions can be made about end stage assessment points and stage duration."