PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 202


Which is a purpose of a quality register?

Show Answer
Correct Answer: B,C

The purpose of a quality register is to provide the status of quality activities carried out for completed products. It serves to summarize all the quality management activities that are planned or have taken place. It provides an overview and status of all quality activities and helps in reporting for the end stage and end project reports.

Discussion

12 comments
Sign in to comment
asalimOption: C
Aug 6, 2020

C is the correct answer. A quality register is used to summarize all the quality management activities that are planned or have taken place, and provides information for the end stage reports and end project report

ShaniseOption: C
Sep 8, 2020

C is correct.

FarbodOption: C
Feb 25, 2021

C is correct answer. "Quality register: A quality register is used to summarize all the quality management activities that are planned or have taken place, and provides information for the end stage reports and end project report."

ConstanzaOption: C
Jan 24, 2021

C is the correct answer

Wombat1987Option: C
Apr 1, 2021

The correct answer is C. Since it has nothing to do with "issues". https://prince2.wiki/management-products/quality-register/ I like to say that a Quality Register does three things: Provides an overview of the planned quality activities and provides a unique reference for each quality activity. Provides an overview on the status of all quality activities and a pointer to the quality records. And at the end of the project, it provides a history of all quality activities that have taken place and all results.

Martin77Option: C
Apr 15, 2021

The quality register is updated to reflect (in summary form) the actual results from the quality activities. The quality register provides key audit and assurance information, relating what was planned and agreed (in the quality management approach and product descriptions) to the quality activities actually performed . prince2 guide, 8.2 C should be correct

AliSamiOption: C
Apr 24, 2022

C. is the correct answer

GetRajOption: A
Jul 5, 2020

A seems to be correct

VikceOption: A
Jul 9, 2020

agree, A is correct

LenlenlenOption: A
Jul 24, 2020

A it is

MehanOption: A
Jan 17, 2021

A seems to be a more precise answer

bes_iOption: C
Jul 20, 2024

C. A quality register is used to document the quality control activities and status for the project's products. It helps track and manage quality-related activities and issues throughout the project, ensuring that the deliverables meet the required quality standards.