PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 265


DRAG DROP -

PLANS -

The project manager is preparing the stage 3 plan and has asked the team manager for the 'amended course booking procedures' work package to prepare the team plan at the same time.

Here are three actions that will need to be carried out when preparing these plans.

Which role (A-F) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
MortenC
Feb 11, 2023

First:Project support 7.2.1.9 Second: Senior User? Third: Team Manager?

RGohel
Sep 1, 2023

1. Project support 2. Senior User 3. Team manager Ref: 9.2.2 page 101

ravi_aws
Oct 7, 2023

Project support, senior user, team manager