How does the project plan help to support the 'manage by stages' principle?
How does the project plan help to support the 'manage by stages' principle?
The project plan supports the 'manage by stages' principle by identifying the major control points and milestones. This principle is about breaking the project into more manageable and controllable stages. By clearly outlining the major control points and milestones, the plan allows for effective monitoring and control of the project's progress, ensuring that any issues can be addressed promptly at the end of each stage.
C. seems correct (best), but D. is correct too The Project Plan is a high-level plan and is mainly used by the Project Board. It provides a statement of how and when a project’s time, cost, scope and quality targets are to be achieved. The Project Plan shows the major products, activities and resources required for the project. https://prince2.wiki/theme/plans/