Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 247

As part of the 'closing a project' process, an announcement is to be made that ABC Company's 'capability to deliver health and safety training' is now ready for launch and the project has been closed.

Which role should prepare the draft of the announcement?

    Correct Answer: D

    The project manager is responsible for creating all the necessary project documentation, including drafting announcements about the project's completion and readiness for launch. This role ensures that all communications are accurate and consistent with the project's objectives and outcomes. Once the draft is prepared by the project manager, it may be reviewed and approved by the executive or other senior roles, but the initial draft preparation is typically the responsibility of the project manager.

Discussion
ravi_awsOption: B

announcement is usually made by the Executive

ravi_aws

B - Exec

ravi_aws

But drat will be created by Project manager so right answer is PM