Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 119

How is the tailoring approach defined for a project?

    Correct Answer: A

    The project board is responsible for approving the tailoring approach for a project. The approval process ensures that the approach aligns with the project's objectives and requirements. The project manager typically identifies and documents the tailoring, but the final approval rests with the project board.

Discussion
ebarb

ridiculous question

Chucky2Option: A

A is correct The project board is responsible for approving the tailoring approach. But it is the responsibility of the PM to identify and document the level of tailoring in the project

omande

4.3.2: The project manager is responsible for identifying and documenting the level of tailoring for the project. Tailoring affects how a project is managed and so it is documented as part of the PID, which is reviewed by the appropriate stakeholders and approved by the project board.

VJ80Option: A

This question is misleading as there is difference between defining and approving. However the answer is chosen based on best fit as the other options are not correct.