PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 119


How is the tailoring approach defined for a project?

Show Answer
Correct Answer: A

The project board is responsible for approving the tailoring approach for a project. The approval process ensures that the approach aligns with the project's objectives and requirements. The project manager typically identifies and documents the tailoring, but the final approval rests with the project board.

Discussion

4 comments
Sign in to comment
ebarb
Nov 4, 2021

ridiculous question

Chucky2Option: A
Dec 1, 2022

A is correct The project board is responsible for approving the tailoring approach. But it is the responsibility of the PM to identify and document the level of tailoring in the project

omande
Oct 23, 2023

4.3.2: The project manager is responsible for identifying and documenting the level of tailoring for the project. Tailoring affects how a project is managed and so it is documented as part of the PID, which is reviewed by the appropriate stakeholders and approved by the project board.

VJ80Option: A
Dec 12, 2022

This question is misleading as there is difference between defining and approving. However the answer is chosen based on best fit as the other options are not correct.