Which management level should approve a course of action if project-level tolerance is exceeded?
Which management level should approve a course of action if project-level tolerance is exceeded?
The Project Board is responsible for overseeing the project's direction and approving any course of action when project-level tolerance is exceeded. This ensures the project remains aligned with its objectives and business case, making them the appropriate management level for such decisions.
B. Project board In PRINCE2, the Project Board is responsible for approving any course of action when the project exceeds its tolerances. This level of management oversees the project’s overall direction and makes decisions regarding significant deviations from the project plan, ensuring that the project remains aligned with its business case and objectives.