PRINCE2-Foundation Exam - Question 216


Which project management team role can be combined with business assurance?

Show Answer
Correct Answer: A,C

The role that can be combined with business assurance in a project management team is the Executive. In a project, the Executive is responsible for ensuring the project remains aligned with the business objectives and can take on the business assurance role, which includes ensuring the business case is valid, the project's value is optimized, and the project remains aligned with strategic goals.

Discussion

6 comments
Sign in to comment
theotenisOption: C
May 12, 2021

Correct answer is C. From the URL provided in the answer: "An important responsibility of the PRINCE2 project board is project assurance. This is part of the PRINCE2 project management team, and consists of three roles, business assurance, user assurance, and supplier assurance. "

Martin77Option: C
May 18, 2021

I agree - C is correct (Executive) Executive = Business Assurance, Senior Supplier = Supplier Assurance, Senior User = User Assurange

AliSamiOption: C
Apr 24, 2022

C is the correct answer

jj0097Option: C
Jul 7, 2022

definitely C

Mo1977
Jul 26, 2022

Thanks JJ

isuweeraOption: C
Mar 15, 2023

Answer C - Executive = Business Assurance

bes_iOption: A
Jul 20, 2024

A. Project Support Project Support can be combined with the Business Assurance role, as both roles involve aspects of ensuring the project meets its requirements and delivers value. Business Assurance focuses on ensuring that the project is aligned with business needs and provides assurance that the project is adhering to required standards. Project Support can take on additional responsibilities related to assurance activities, including maintaining documentation and supporting compliance with project standards