In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
In the context of PRINCE2, 'Managing Product Delivery' describes the process that acts as a link between the team manager and the project manager, ensuring that products are created, delivered, and accepted as specified. This process involves the team manager, who manages the work, and the project manager, who oversees the project's progress and delivery according to PRINCE2 guidelines.
B is correct