PRINCE2-Foundation Exam - Question 34


Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Show Answer
Correct Answer: C

The Project Initiation Documentation serves two main purposes: First, it provides a sound basis before the Project Board authorizes the project, ensuring that there is a clear understanding and agreement about the scope, approach, and objectives of the project. Second, it is a living document that should be updated at the end of each stage to reflect the current status and any changes that have occurred, ensuring that project documentation remains accurate and up-to-date. Therefore, both statements are true.

Discussion

10 comments
Sign in to comment
OridanDestaOption: B
Jun 28, 2022

B is correct, authorization is already given in this stage. the project board should commit on the PID. if not, the second stage will be closing the project. (as it is already started, the PID is part of the initiating a project) which can only start after authorization

Tatina1Option: C
Oct 26, 2020

I think both are true because the Project Board do two authorisations: Firs the authorize an initiation after starting up a project process and then the authorize a project after the initiating a project process

Junior_SimOption: C
May 19, 2021

Both of it is correct. Based on the manual A.20

peppeOption: C
Oct 15, 2021

C is correct

GoseuOption: B
Nov 28, 2021

As is the correct answer is B . C would be correct if the answer was Ensure that the project has a sound basis before asking the project board to make any major commitment to the project . The board at this point has already authorized the project . This has to do with continued business justification .

omandeOption: C
Aug 10, 2023

For 1.: According to A.20: One of the three primary uses of the PID is "to ensure that the project has a sound basis before asking the project board to make any major commitment to the project". Here, a major commitment is being referred as the authorization of the project, which takes place in the Directing a project process, after the PID has been assembled in the Initiating a project process and the authority from the project board to deliver the project has been requested (see also 16.4.9). For 2. "The PID is a living product in that it should always reflect the current status, plans and controls of the project. Its component products will need to be updated and re-baselined, as necessary, at the end of each management stage, to reflect the current status of its constituent parts." (From A.20)

egsakOption: B
Sep 23, 2020

only 2nd statement is true because project already authorized at that time

FarbodOption: B
Feb 27, 2021

B is the correct answer, (PID) is to define the project, in order to form the basis for its management and an assessment of its overall success. (PID is created after project approved)(during the Initiation initiation process not before before project approval))

Farbod
Feb 27, 2021

I misspoke, both are correct, it is needed for project authorization. so C.

Farbod
Feb 27, 2021

I misspoke, both are correct, it is needed for project authorization. so C.

test235Option: B
Dec 17, 2023

Correct answer is B and not C.

tarikaygulOption: C
Dec 19, 2023

C is correct. The PID is a living document and will need to be updated and re-baselined, as necessary, at the end of each management stage to reflect current status.