Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 292

As part of the 'authorize a work package' activity, the project manager is preparing the work package for the marketing materials. The project manager has asked the team manager for this work package to draft some specialist sections of the work package. The project manager and project assurance will review these sections before the work package is authorized.

Is this an appropriate action, and why?

    Correct Answer: B

    Yes, because the project manager is responsible for authorizing the work package even if its preparation is delegated. The project manager has the overall responsibility for the work package and can delegate the preparation to experts or team managers. Project assurance will review to ensure that the work package meets the required standards before it is authorized.

Discussion
ravi_awsOption: B

Yes, because the project manager is responsible for authorizing the work package even if its preparation is delegated