Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 256

In which process is the work to be done assigned to a team manager?

    Correct Answer: D

    In project management, the process of assigning work specifically to the team manager is referred to as 'Managing product delivery'. In this process, the team manager is given the responsibility to handle the work packages and ensure that the deliverables are produced according to the specified quality and timeline. This is different from 'Controlling a stage', which is focused on monitoring and controlling the progress of a project stage, and 'Managing a stage boundary', which deals with the transition between different stages of the project.

Discussion
proletOption: C

During Controlling a stage process the work to be done is assigned, as within the Managing product delivery the assigned work is executed.

El_CabronOption: D

The answer is clearly D. Examtopics, where do you get these answers??