The quality review of the 'training venue specifications' reported that no quality criteria had been decided for the geographical location of the venues. In a previous project, there was low attendance at the training events because delegates were required to travel a long distance, which caused a risk to the project. Therefore, the executive is concerned if project risk processes are being followed and has asked project assurance to audit the application of the Health and Safety Training
Project's risk -
management approach.
Is this an appropriate application of the 'risk' theme, and why?