Question 229

The quality review of the 'training venue specifications' reported that no quality criteria had been decided for the geographical location of the venues. In a previous project, there was low attendance at the training events because delegates were required to travel a long distance, which caused a risk to the project. Therefore, the executive is concerned if project risk processes are being followed and has asked project assurance to audit the application of the Health and Safety Training

Project's risk -

management approach.

Is this an appropriate application of the 'risk' theme, and why?

    Correct Answer: B

    The appropriate application of the 'risk' theme is that a review ensures the risk management approach has been properly implemented. Ensuring that risk management techniques are correctly applied is crucial for identifying and mitigating potential risks, such as the geographical location of the venues impacting attendance. This proactive step will help to prevent problems that could arise from insufficient risk management.

Discussion
ravi_awsOption: B

A is more generic. B tackles the specific issue.

ameyaenggOption: B

Correct Answer : B