Question 167

When should the level of tailoring be defined?

    Correct Answer: A

    The level of tailoring should be defined during the initiation stage of a project. This is when the project team assesses the specific needs and characteristics of the project to determine which PRINCE2 processes, themes, and management products need to be applied and to what extent they should be tailored. By establishing the level of tailoring early, the project can be managed consistently and effectively from the outset, ensuring that the methodology is appropriately adapted to suit the project's environment and requirements.

Discussion
GetRajOption: A

Level of tailoring is agreed during the Initiation

Martin77Option: A

A is correct. Reference Prince2 guide, Figure 16.1 Overview of initiating a project the fist step is "Agree the tailoring requirements"

MehanOption: A

A is correct

sohrabianiOption: A

A is correct - During IP tailoring will be done by PM

sohrabianiOption: A

The Answer is A Because during IP the PID which contains the tailored items would be provided

ShaniseOption: A

Tailoring is documented by project manager during PID and approval by the project board. Answer should be A.

AnapellicerOption: D

While issues and risks experienced during the project may prompt a review of the level of tailoring, it is important to define the level of tailoring upfront to ensure that the project is set up for success from the outset. Therefore, option D (before the project is triggered by the project mandate) is the correct answer.

chriscilia81

The trigger (project mandate) happens before anything else. Refer to Figure 14.1 and the related text.

renzaOption: A

A is the right answer

Haranp12Option: A

It’s definitely A

TesteurtestOption: A

The Project Initiation Documentation should describe how the PRINCE2 method is tailored for that particular project https://prince2.wiki/principles/tailor-to-suit-the-project-environment/

RznNsrOption: A

A is correct. Dear Admin, pls update the answer for those who are wrong. i can see many of those which is really confusing even we select the right answer.

skshah47Option: A

A seem correct! According to PRINCE2, the level of tailoring should be defined during the initiation stage. At this stage, the project team assesses the level of tailoring required for the project and identifies which PRINCE2 processes, themes, and management products are necessary to be applied. By defining the level of tailoring early in the project, the team can ensure that the project is managed consistently and effectively throughout its lifecycle, while also being tailored to the specific needs and characteristics of the project.