Question 56

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

    Correct Answer: B

    Quality must be managed to ensure the project's products are fit for purpose. Managing quality involves defining standards and criteria that the project's products need to meet, ensuring they fulfill the intended requirements and achieve customer satisfaction.

Discussion
a2d1fd1Option: B

QUALITY: defines standards delivered scope must meet to be fit for purpose.