Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Show Answer
Correct Answer: B

Quality must be managed to ensure the project's products are fit for purpose. Managing quality involves defining standards and criteria that the project's products need to meet, ensuring they fulfill the intended requirements and achieve customer satisfaction.

Discussion

1 comment
Sign in to comment
a2d1fd1Option: B
Apr 16, 2024

QUALITY: defines standards delivered scope must meet to be fit for purpose.