Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 211

During the delivery of the initial pilot course, an issue was raised about the technology defined in the 'training venue specifications'. During project closure, the project manager confirmed that the issue was recorded in the issue log and an entry in the daily log recorded how it had been resolved for the remaining pilot courses. The project manager then produced a related lessons report.

Is this an appropriate application of the 'learn from experience' principle, and why?

    Correct Answer: A

    Yes, because a lessons report must be produced as part of the 'closing a project' process. Recording and reporting lessons learned is a key activity during project closure to ensure that valuable insights are documented and shared for future projects.

Discussion
kuku1789Option: B

it is B