In which process does the project manager monitor the work assigned to a team manager?
In which process does the project manager monitor the work assigned to a team manager?
In project management, specifically within the PRINCE2 framework, the process where the project manager monitors the work assigned to a team manager is 'Controlling a stage'. This process involves assigning work, monitoring its progress, dealing with issues, and ensuring that the stage remains within its tolerances. This makes it the correct answer over other processes like 'Managing a stage boundary' or 'Managing product delivery', which have different focuses within the project management stages.
D is correct Ref:18.1
17.1 Purpose Planned risk responses need to be actioned, their effectiveness monitored and corrective action taken where responses do not match expectations.
Correction: The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.
In PRINCE2, the process where the project manager monitors the work assigned to a team manager is called "Managing a Stage Boundary". This process is part of the "Controlling a Stage" process, which is one of the seven processes in the PRINCE2 framework.
The Project Manager does the directing, not the Team Manager which is responsible for product delivery only.
the controlling*
https://prince2.wiki/processes/controlling-a-stage/#:~:text=The%20purpose%20of%20the%20Controlling,the%20stage%20remains%20within%20tolerance.