Which action should the project manager take during the ‘assessing issues’ step?
Which action should the project manager take during the ‘assessing issues’ step?
During the 'assessing issues' step, the project manager should determine the initial priority of the issue that has been raised. This is necessary to understand the significance and urgency of the issue before considering alternative options for resolution or requesting feedback from the project board.
Option B is correct as per the contents in Prince2 6th Edition pocket Guide
D 11.4.2 Assessing issues It may be necessary to request advice from the project board to check its understanding of the issue’s priority or severity before proposing resolutions