Question 258

Which statement about project roles is CORRECT?

    Correct Answer: D

    In PRINCE2, it is crucial that the responsibilities defined in the methodology are fulfilled, but project roles can be customized according to the specific needs of the project. This flexibility allows project managers to adapt the roles to fit the context and requirements of their particular project while still adhering to the fundamental principles and responsibilities outlined in PRINCE2.