The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
The Manage by Exception principle in project management typically sets tolerances for Time, Cost, Quality, Scope, Risk, and Benefit. These six areas are crucial for monitoring and controlling project performance. Tolerances are established to provide the project manager and team with predefined limits for acceptable performance variations. This allows for effective decision-making and control when deviations occur, ensuring the project stays on track to meet its objectives.
I remember them like this - SQR (like square) TBC. So "Square TBC" haha
correct answer D. Section 3.5 prince 2 manual