Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 87

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

    Correct Answer: C

    During a quality review meeting, it is important that any identified defects are formally addressed through agreed-upon actions. Therefore, 'the agreed actions should be recorded for' fits best in the sentence as it emphasizes documenting the specific steps to be taken for resolving defects. This ensures accountability and a clear plan for addressing issues found during the review.

Discussion
lucafrancoOption: C

C should be correct: 8.4.5 The review team agrees actions on each question as it is raised. The administrator records the actions and responsibilities