Question 334

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.

The Stage Plan for stage 3 has been produced.

The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.

None of the ֲ£500 change budget has been used to date and this is available for the stage.

Which 2 statements apply to the External dependencies section?

    Correct Answer: A, E

    Entry 5, regarding the new company logo, should be deleted because it is being delivered by a separate project and will be detailed in the plans for that project, making it not relevant as an external dependency here. Entry 7 should be deleted as well since this dependency should be captured in the Product Description for the label design, not in the external dependencies section.