Question 185

What additional risk will this place on the project?

    Correct Answer: D

    The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received. This introduces a risk that the outsourcing project might not attract sufficient or suitable bids, which could jeopardize the success of the project. This is a direct and specific additional risk affecting the project's procurement process.

Discussion
pollon

The question should be "If the decision to remove Facilities services from the scope of the Restructuring project, what risk will this introduce to the project?"

pollonOption: D

Answer is D

PetzaOption: A

According to the book "PRINCE2 Foundation Exam Practice Questions & Dumps: 150+ Exam", correct answer is A, section change theme explanation

johnzoids

there is no answer given