Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 294

DRAG DROP -

DIRECTING A PROJECT -

Here are three actions that are carried out as part of the 'directing a project' process.

During which activity (A-E) should the action occur?

Choose only ONE activity for each action. Each activity can be used once, more than once, or not at all.

Select and Place:

    Correct Answer:

Discussion
ravi_aws

1.The act of approving a specific request for a communications expert to assist with the communication management approach is more of an ongoing activity that could occur at any point in the project, not just at the start of a new stage. This is why it falls under "give ad-hoc direction"

ravi_aws

2. Closure 3.It’s about advising the project manager of a change in ABC company’s approach to course delivery. This seems to be more of an ongoing guidance or direction provided to the project manager, rather than a formal authorization of a new stage or exception plan so ad-hoc direction for point 3.