Exam PMP All QuestionsBrowse all questions from this exam
Question 1217

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

    Correct Answer: D

    To begin building an effective high-performing team, the project manager should establish the project scope and set clear team objectives. This ensures that all team members understand the project's goals and their roles in achieving them, creating a solid foundation for all future activities and promoting alignment and coordination.

Discussion
c8ee0e6Option: D

I strongly believe its D. I also confirmed with GPT - Establishing the project scope and setting clear team objectives provides a foundation for all subsequent activities. It ensures that every team member understands what needs to be achieved and what their role is in achieving it. This clarity is essential for forming a cohesive, high-performing team. It aligns everyone's efforts towards common goals and helps in planning, coordination, and setting performance standards effectively.

ELTIGANIOption: C

Select members for their skill or potential.