PMI-100 Exam - Question 275


What tool or technique is used in the Collect Requirements process?

Show Answer
Correct Answer: D

In the Collect Requirements process, prototypes are used as a tool or technique. Prototyping helps stakeholders visualize the final product or service and provides a basis for gathering and refining requirements. By creating mock-ups or models, stakeholders can interact with prototypes, offer feedback, and suggest modifications, which aids in the accurate collection of requirements.

Discussion

4 comments
Sign in to comment
041ba31
Dec 17, 2023

C. Product analysis In the Collect Requirements process of project management, one of the key tools and techniques used is "Product analysis." Product analysis involves examining the characteristics, features, and attributes of the project's end product or deliverable to understand the requirements that need to be gathered. By analyzing the product, project teams can gain a deeper insight into what the final outcome should look like and what specific requirements are necessary to meet stakeholder needs and expectations.

Andrew_1980Option: D
Jul 13, 2024

D for sure (100%)

Andrew_1980
Jul 7, 2024

Sorry 'D' is right - Prototypes. Just mistaken with letter

Andrew_1980Option: C
Jul 7, 2024

C - The right answer is Prototypes (Collecting requirements process). D - is right for Defining the scope process