Exam PgMP All QuestionsBrowse all questions from this exam
Question 17

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

    Correct Answer: C

    The payment to ZAS Corporation depends on what the termination clause of the contract stipulates. Contracts often contain specific terms and conditions regarding termination, including what obligations remain if the work is terminated early. Eric's organization would need to refer to these terms to determine their liability for payment.

Discussion
SergeyKOption: C

C is the right answer

tungdtOption: C

C is make sense