PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 152


A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.

What does this value mean for the project?

Show Answer
Correct Answer: B,C

The value of 0.9024 is the Cost Performance Index (CPI), which is calculated as Earned Value (EV) divided by Actual Cost (AC). A CPI less than 1 indicates that the project is not earning the planned value with respect to the actual cost incurred, meaning the project has started exceeding the planned cost.

Discussion

17 comments
Sign in to comment
pmp_237studentOption: A
Dec 29, 2022

The figure is less than 1 which shows that AC>EV this means the project is earning less value than expected, A should be the right choice here.

PrimacomSHU
Nov 2, 2023

Value is for SPI, rather than CPI

chxzqw
Dec 23, 2022

are both A and B same thing ?

odylecOption: B
Jan 21, 2024

B is the Answer. Here we talk about CPI=EV/AC so its COST.

odylec
Jan 21, 2024

CPI is for Cost and SPI fo Value

akashushi007Option: B
May 19, 2024

B. The project has started exceeding the planned cost This is because the project is earning less value than what was planned for the actual cost incurred

Hashi1_snrOption: B
Nov 19, 2023

I'm voting for B as the correct answer to this question. However, looking at the complicated nature of the question and how it is worded, one will think it's a nonsense question and has no significance. This takes my mind to the fact that there will be 15 questions in the exam that won't be graded whether you answer them correctly or wrongly. So, I'm suspecting this question to be one of those questions that will have no value in the exam but will form part of the 180 questions. so let's don't overemphasize on determining the correct answer to this question when we are seeing it as not properly worded for better understanding. Without prejudice to the exam content, I still consider option B as the correct answer to this question.

Mamoonpk
Nov 28, 2023

Wow. i didnt know that :D

loupsssssOption: C
Dec 12, 2023

C is correct

loupsssss
Dec 12, 2023

EV = 0.9 AC so less cost here, tricky one

DeeskiOption: B
Dec 19, 2023

CPI = EV / AC, Cost Performance Index: An earned value management measure that indicates how efficiently the work is being performed with regard to the budgeted cost of the work.

DeeskiOption: B
Dec 21, 2023

Cost Value = Earned Value – Actual Cost, Negative value mean the project is over budget.

Bruce_LiuOption: A
Dec 25, 2023

CPI=EV/AC, CPI is less than 1 means project is earning less than planned. ChatGPT also got the same answer.

atoms101Option: D
Dec 25, 2023

Since A & B are same, we need to choose option which is balanced which is true in general.

leo9944Option: A
Jan 5, 2024

the answer is A because we are talking value here by presenting CPI

segatarasovOption: A
Feb 27, 2024

C cannot be a correct answer, A is correct A ratio of less than 1 indicates that the project is over budget, while a ratio greater than 1 suggests that the project is under budget. In this case, a ratio of 0.9024 indicates that the project is slightly over budget.

AwaisalamOption: A
Apr 2, 2024

A. The project is earning less value than was planned

MartinussantikaOption: A
Apr 12, 2024

The wording "has started" on B will confusing (since when). But the fact according to PMI also saying earned value must be bigger than actual cost. so answer A is more clear

jiljapOption: C
Apr 26, 2024

If the CV is positive (CV>0), this means that the acquired value is greater than the actual cost (EV-AC>0 or EV>AC) and therefore the project has earned more value than planned, C is correc

nqbaotdOption: A
Jun 6, 2024

CPI= EV/AC < 1, so A is correct

tonybuivannghiaOption: A
Jul 19, 2024

CPI is less than 1, so A is correct