Question 529

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished.

How should the project manager approach this situation?

    Correct Answer: A

    When a project team faces difficulties understanding technical details regarding requirements that are critical for the current iteration, the most effective approach is to request that the customer reviews and clarifies feature definitions for the current sprint. This ensures that the necessary information is provided promptly, allowing the team to proceed with their tasks without delay. Scheduling weekly meetings might be too late to resolve the immediate issue, and sending a burndown chart does not directly address the need for clarification on the requirements.

Discussion
SteAleOption: A

Who else can help to clarify the requirements?!

DavidTriOption: A

it's critical to impact to currrent iteration so PM need to send request to customer to review and clarify these info. schedule weekly meeting is late and maybe impact to iteration delivery

victory108Option: A

A. Request that the customer reviews and clarifies feature definitions for the current sprint

Bobbie30Option: D

Why not D in order to include future sprints with the current sprint being a part of them

PMPStudent

Because they need to connect as soon as possible. The issue needs to be resolved for the current iteration to be successful.