The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
The work breakdown structure (WBS) is a key input for schedule metrics because it provides a hierarchical decomposition of the total scope of work to accomplish the project objectives. By analyzing the WBS, the risk manager can track progress, identify milestones, and monitor schedule performance against planned activities. It helps in setting baseline expectations and assessing actual performance against the schedule. This makes the WBS an essential tool in the monitoring and reporting of schedule metrics.
Critical Path Method is a technique and cannot be an input.
By analyzing the WBS, project manager can track progress, identify milestones and monitor schedule performance against planned activities. Additionally, it is an output/input, not a tool&technique.
I agree with Azharmak… C
I thought it should be Critical Path Method for Schedule.