A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does not have a requirement for it.
What should the project manager do?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does not have a requirement for it.
What should the project manager do?
When a client lacks an appropriate knowledge management system and does not have a requirement for it, the project manager should coordinate with the team and project stakeholders to collect the necessary knowledge. This approach ensures that all relevant information is gathered, shared, and maintained systematically, leveraging the collective input of all parties involved.
D is right answer.
D. Coordinate with the team and the project stakeholders to collect the knowledge.
D. Coordinate with the team and the project stakeholders to collect the knowledge