Exam PMI-ACP All QuestionsBrowse all questions from this exam
Question 31

When prioritizing features to be delivered in an iteration, on what should an agile team defer work?

    Correct Answer: C

    When prioritizing features to be delivered in an iteration, an agile team should defer work on low-risk and low-value features. This approach allows the team to focus on high-value tasks that are crucial for the project's success. High-risk features are also prioritized to address potential challenges early on. Low-risk and low-value features can be postponed as they do not significantly impact the project's outcome and can be dealt with when there are available resources.

Discussion
abhi517Option: C

When prioritizing features to be delivered in an iteration, an agile team should defer work on low-risk and low-value features. Therefore, the correct option is C. Low-risk and low-value. Agile teams should prioritize high-risk and high-value features to be delivered first, followed by low-risk and high-value features. Low-risk and low-value features should be considered for deferral to future iterations, as they are not critical to the success of the project and can be postponed to focus on more important items.

Agile_Dario_Conde

I agree

Michaela0015Option: B

B is correct. "Defer work on all low-value features, especially those that are also high risk." https://www.linkedin.com/pulse/agile-planning-prioritization-desirability-borjan-petreski

ELTIGANI

The shared article confirms that C is the correct answer (Low-Value & Low-Risk items should be delayed).

NervysOption: B

B for sure

NorWEEDOption: B

B. High-risk and low-value. Explanation: The goal in Agile is to deliver the most valuable features as early as possible and to tackle risks while doing so. Thus, features that are high-risk and high-value should not be deferred but tackled head-on. On the contrary, features that are high-risk and low-value don't provide enough value to justify the associated risk, so these should be deferred or even avoided. Low-risk and high-value features (Option D) are desirable as they give the team valuable output with minimal risk. Low-risk and low-value features (Option C) could be deferred or might be tackled as time and resources allow, but they wouldn't be a first priority. Remember, the goal is to provide the maximum value with minimal risk, and the team should focus on high-value work first. The risk is considered to ensure that potential problems are dealt with sooner rather than later.

PetrevskiOption: B

A = high priority - do first B = low priority - avoid / defer (correct) C = medium priority - do last D = medium priority - do second

tuanphongpro123Option: C

C is correct. https://university.hygger.io/en/articles/2399041-value-vs-risk-model

Holly2023Option: C

C, low risk & low value = do last ==> defer It's not B because high risk & low value = avoid

Notmeforsure

I think this answer makes more sense

zayn_1983Option: A

High value and high risk features should be prioritized, then high-value low-risk, finally low-value and low-risk.

HenryBachOption: B

B is correct

195daa8Option: B

Option B aligns with Lean principles, specifically the concept of value stream mapping, which is used to visualize the steps involved in delivering value to the customer and identify opportunities for improvement. By reviewing the process value stream, the agile team can analyze the efficiency of the current process activities and identify areas where improvements can be made to enhance efficiency and effectiveness.

itsmewajidOption: C

High Risk High value can't be deffered.

ImrangoshiOption: C

high risk means, making mistakes and learning if there is any challenge in it.

ImGonnaPassIt

High-risk and low-value features present a high potential cost in terms of risk without a corresponding high level of benefit, making them a lower priority compared to features that either offer higher value or come with lower risk. Prioritizing high-value work that aligns with the product vision and customer needs is key in Agile development, while risks should be managed strategically.

ImrangoshiOption: C

C is the Correct Answer

InvisibleBeingOption: B

I believe the correct answer is B. The item with the lowest value and high-risk is the worst in the product backlog. What it means is that there are many risks involved with the item, but the value earned is very little. It is not worth the risk, where value driven is less than what it costs to mitigate risks.

NhuhoOption: B

B High-risk and low-value

ChikhalsoukOption: B

High-risk and low-value

jjjOption: D

High-value, low-risk: Items that should be prioritized.