Question 230

A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component project requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.

What is a critical component of the Program Schedule Management Process?

    Correct Answer: B

    A critical component of the Program Schedule Management Process is the activity or component start and finish dates, as well as intermediate milestones. These elements are essential for effective schedule management as they allow the program manager to track progress against the plan, identify deviations, and take corrective actions to prevent budget overruns.

Discussion
CornersOption: B

+1. It is B.

tsangcklOption: B

I pick B. Other options is not in the Program schedule management plan.

LuanNDOption: B

Totally agree with B SPM 5, page 169. 170

[Removed]Option: B

B. Activity or component start and finish dates, as well as intermediate milestones. This element is essential for effective schedule management as it helps in tracking progress against the plan. Knowing when activities are supposed to start and finish, along with key milestones, allows the program manager to monitor progress, identify deviations from the plan, and take corrective actions to prevent budget overruns.

hanyulinOption: B

B correct

ekk1983Option: B

I would say B