A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
After onboarding resources to start work on a project, the project manager will update the resource management plan and the cost baseline. The resource management plan outlines how resources will be identified, acquired, utilized, and managed, so it must be updated to reflect the newly onboarded resources. The cost baseline, which represents the authorized budget for the project's work, also needs to be updated to account for any changes in project costs due to the onboarded resources, such as salaries or contractor fees.
Resource management plan: This document outlines how resources (both human and physical) will be identified, acquired, utilized, and managed throughout the project. After onboarding resources, updates to this plan may include new roles filled, changes in resource availability or capacity, and any adjustments to resource allocation strategies. Cost baseline: The cost baseline is a part of the overall project baseline and represents the authorized budget for the project work. Onboarding resources can impact project costs, such as salaries, contractor fees, or other resource-related expenses. Therefore, updates to the cost baseline may be necessary to reflect these changes. Preassignment refers to assigning specific resources to project roles BEFORE the project officially begins. Onboarding resources happens after the decision is made to bring them onto the project. This could be considered if it’s “Reassignment”.