Question 81

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds.

What should the project manager do?

    Correct Answer: C

    The best course of action for the project manager is to review the lessons learned from similar projects that were executed previously. By understanding what led to the low performance in the other department, the project manager can identify potential pitfalls and take preventive measures to ensure that their project does not encounter the same issues. This approach leverages past experiences to improve future project performance.

Discussion
TrollemOption: C

Last 10 questions is too obvious...

martinx84Option: C

Review lessons learned

AsakthiOption: B

B add an external expert

victory108Option: C

C. Review the lessons learned on similar projects so that they do not fall back into the same pattern

DinhleOption: C

Shoub be C. Experience from similar project

GanzeeOption: C

C. Review the lessons learned on similar projects so that they do not fall back into the same pattern.