Exam PMI-RMP All QuestionsBrowse all questions from this exam
Question 129

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

    Correct Answer: B

    The project manager should apply an iterative approach to risk identification. Since multiple new risks have come up and were not included in the risk register, it is crucial to continuously revisit and update the risk management process. An iterative approach ensures that new risks are identified and addressed promptly, enhancing the overall risk management framework.

Discussion
MikeMarloOption: D

Next thing to do is to Develop some plans for the present risks that we have in the Project. In order, it will be: D, B, A, C