Question 45

You are the program manager for your organization and you're dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?

    Correct Answer: B

    In program management, it is crucial to document issues in an issue register. This register is specifically used to capture and track issues that have already occurred or need attention, ensuring that they are monitored and resolved accordingly. Recording these issues allows for better tracking, transparency, and accountability throughout the resolution process.

Discussion
tungdtOption: C

C is correct answer

UHSOption: B

b is issue register (more like issue log to documents events that have occurred) and D is risk register(events may potentially occur)

Cindyl

what is the difference between B and D?

fido_dido

A risk is not materialized, when a risk materializes it becomes an issue