PMP Exam QuestionsBrowse all questions from this exam

PMP Exam - Question 1221


During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned. What should the project manager do?

Show Answer
Correct Answer: D

When a stakeholder indicates that a main feature from the contract is not applicable and this is documented in the lessons learned, the project manager should first verify the accuracy of this information. Ensuring that the lessons learned documentation is correct and up-to-date is crucial before taking any further steps. This verification will help in understanding the root cause of the discrepancy and in preventing any misunderstandings or errors in project execution.

Discussion

2 comments
Sign in to comment
ELTIGANIOption: C
Jun 5, 2024

C. Check with the team to learn what can be done, and consult an expert.

martinx84Option: D
Jul 21, 2024

Check that this information is documented