During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned. What should the project manager do?
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned. What should the project manager do?
When a stakeholder indicates that a main feature from the contract is not applicable and this is documented in the lessons learned, the project manager should first verify the accuracy of this information. Ensuring that the lessons learned documentation is correct and up-to-date is crucial before taking any further steps. This verification will help in understanding the root cause of the discrepancy and in preventing any misunderstandings or errors in project execution.
Check that this information is documented
C. Check with the team to learn what can be done, and consult an expert.